ERECTION OF CARBON BURN-OUT BOILER PLANT The Carbon Burn Out boiler utilises fly ash and bed ash deposits from existing operating boilers as a fuel to generate steam and deposits with reduced carbon content. The project included the construction of a fluidized bed Thermax boiler of capacity 16.2 TPH, and pressure 16 bars. List of [...]
Boiler Relocation Project
The Medine Sugar Factory upgraded its existing capacity of electricity generation with the addition of a 70 kW John Thompson boiler transferred from Union St Aubin Sugar Factory. The boiler and its associated equipment, piping, pressure parts, impulse line and ducting were dismantled, refurbished, installed and commissioned during a ten months period.
Terragen Ltd
Work on Grid TR1
Omnicane-Savannah
Dismantle Oliver Filter press unit & accessories & erect same back
Savannah- Omnicane
Realign and level gantry beams and rails using rubber pads and fixing clips
Omnicane/CTDS
Replacement of Roof Sheets on Ash Silo
Holcim (Mauritius) Ltd
Repair of Silencer