ERECTION OF CARBON BURN-OUT BOILER PLANT The Carbon Burn Out boiler utilises fly ash and bed ash deposits from existing operating boilers as a fuel to generate steam and deposits with reduced carbon content. The project included the construction of a fluidized bed Thermax boiler of capacity 16.2 TPH, and pressure 16 bars. List of [...]
Boiler Relocation Project
The Medine Sugar Factory upgraded its existing capacity of electricity generation with the addition of a 70 kW John Thompson boiler transferred from Union St Aubin Sugar Factory. The boiler and its associated equipment, piping, pressure parts, impulse line and ducting were dismantled, refurbished, installed and commissioned during a ten months period.
Fuel Steam and Power Generation
Repair of Boiler Tubes
Centrale Thermique de Belle Vue
Erection of 2 x 140 TPH Boilers Erection of Coal/Bagasse Handling 900 tons. Manufacture of 2 x ESP and 2 x G Collectors
Lonrho Sugar
3 of (42 x 84) mills from Reunion Island to Malawi
Shell International
LPG Vessels - Supply and Erection
CIE Thermique du Sud (CTDS)
EPC Turnkey Project for Coal Powerplant at Union St Aubin (35 MW)
CIE Thermique de Savannah (CTSAV)
EPC Turnkey Project for Coal Powerplant at Union St Aubin (45 MW x 2)